| Feb '02 |
The Premier of Victoria, Steve Bracks, announced the development of a purpose-built 1000-seat recital hall and a new 500-seat theatre for the Melbourne Theatre Company
|
| Dec '03 |
Recital Hall Brief developed
|
| Feb '04 |
Design commences
|
| Mar '04 |
Interim Melbourne Recital Centre Board established; Jim Cousins AO, Chairman
|
| Nov '05 |
Independent governance and Board of Directors for Melbourne Recital Centre Ltd approved by State Cabinet
Demolition on site commences
|
| Mar '06 |
Melbourne Recital Centre Limited incorporated
|
| Jun '06 |
Bovis Lend Lease awarded construction contract
|
| Jul '06 |
Construction begins
|
| 2009 |
Opening |